COVID-19, Force Majeure and Delay Notice
Mar 17 2020
On March 11, 2020, Governor Ducey declared a state of emergency in Arizona due to COVID-19. Even before this declaration, COVID-19 and the public reaction to it had begun to affect commercial activity. Financial markets are stressed, use of air transportation is discouraged (and in some cases prohibited), employees are being instructed to work from home, and schools are being closed, to name a few. It is likely that COVID-19 will impact contractors and owners and the construction industry at large. As COVID-19 plays out, the hope and expectation is that those affected will work together to control and minimize personal, health and commercial impacts. As we do that, it is important to ensure contract compliance, proper notice, open communications, and other steps to minimize project and commercial impacts.
Most or all of your contracts likely include force majeure clauses that could entitle you to an extension of contract time if required due to force majeure events. Your contracts very likely include a force majeure clause of some type and perhaps a definition of force majeure event.
Here are some examples within the industry:
Here is a provision from the MAG Specifications addressing this issue (MAG Spec section 108.7):
Each set of circumstances is different, and these are not one-size-fits-all matters. And, while the particular force majeure or delay provision itself may be significant on a particular project if the owner and contractor cannot resolve how to address any impacts, the important point now, and the purpose of this bulletin, is for you to be aware of this issue and to consider whether and when to put owners on notice of potential impacts. The Governor’s declaration of emergency may be a particular starting point, in addition to any impacts already being felt through society very broadly and generally. If you have or are experiencing any specific impacts now (such as labor shortages due to employee absences or supply chain problems), it is a good idea to consider whether you should provide notice that addresses these specific impacts in the notice. We assume (but do not know) that you are not experiencing any significant problems yet, but they may be coming.
Other Action Items and Issues
In addition to considering contractual notice or other requirements, it may make sense to consult with insurance agents or risk managers, as appropriate, to determine whether any of your insurance coverages may apply under these circumstances.
And, as contractors begin placing owners on notice of possible delays and impacts, it makes sense that Owners will begin to search for options that protect their interests such as work suspensions or terminations for convenience. Given the broad use of clauses permitting convenience suspensions and terminations, Owners may use these options in an effort to limit their risk and downside exposure. Accordingly, there are many issues to consider and it may make sense to keep this possibility in mind when giving any notice and to communicate very clearly a desire to be cooperative and to work through our collective health crisis in a fair and sensible manner.
Please note that this email is intended to educate you, in general, about some potential effects of COVID-19 that may impact the construction industry. As noted above, this should not be construed as legal advice, and no new attorney-client engagement is intended. Nor is this bulletin intended to be comprehensive with respect to the potential impacts of COVID-19 on your business or the industry in general. We cannot advise you on these issues without knowing the specifics of your situation, the specific project at issue and the applicable contract language.